Future-Dated Order (FDO) Blocked Before Existing FDO on Asset

게시 일자: Oct 14, 2026
상세 설명

Issue

An asset already has a future-dated order, for example a termination (disconnect) order. When you try to create another order for the same asset with an earlier date, for example a modify order, Industries CPQ doesn't create the order.

Example scenario

  1. An account has an existing asset.
  2. You create a future-dated termination order for the asset with a date of September 30. The order stays in Draft status and isn't activated.
  3. You start a modify order for the same asset and choose September 1, which is earlier than the termination order.
  4. The modify order isn't created.

Symptoms

  • You can't create an order for an asset when the order date is earlier than an existing future-dated order on that asset.
  • The order is blocked whatever the status of the existing future-dated order, including Draft.
  • If you choose a date after the existing future-dated order, you can create the order.

Root Cause

This is a current product limitation, not a configuration error. 

Before Industries CPQ creates a future-dated order, a validation checks the future-dated orders that already exist on the asset. The validation allows a new future-dated order only when its date is after the existing future-dated order on that asset. It doesn't create an order dated before an existing one.

The validation doesn't consider the status of the existing order. A Draft order that isn't activated still blocks an earlier-dated order.

For background on how future-dated orders work, see Future-Dated Orders and Order Queuing in CPQ on Salesforce Help.

솔루션

Industries CPQ doesn't support creating a future-dated order that is dated before an existing future-dated order on the same asset. Use these steps to confirm the cause and choose a way forward.

Confirm the cause

  1. Identify the orders that already exist for the asset.
  2. Check whether the asset has a future-dated order that isn't fulfilled, in any status, including Draft.
  3. Compare dates. If the new order's date is earlier than the existing future-dated order's date, this article applies.
  4. Test with a date after the existing future-dated order. If that order is created, you have confirmed the cause.
  5. If the order is still blocked when its date is later than the existing future-dated order, a different cause applies. Contact Salesforce Support and include the asset's order history (order types, dates, and statuses).

Choose a path forward

  • Option A: Date the new order after the existing future-dated order. If your business process allows it, choose a date later than the existing future-dated order.
  • Option B: Request the enhancement. If you need to create an order before an existing future-dated order, post an idea on Salesforce IdeaExchange. Describe the business value and the experience you expect. Product teams use IdeaExchange to prioritize future enhancements.
추가 자원
  • Validation API: The validation that decides whether a future-dated order can be created is OmniFDOWrapper.canCreateFDO. It returns false for the scenario in this article, whatever the status of the existing order. 
  • Confirmation: The internal expertise team confirmed that you can create future-dated orders only after an existing future-dated order, not before it.
  • Voice of the customer: After the customer posts the IdeaExchange idea, get the idea link and raise a voice-of-customer request for the customer.
Knowledge 기사 번호