Field Service - No Candidates Found: Arrival Window Past Scheduling Horizon

Publish Date: Sep 16, 2026
Description

When using the Book Appointment action or the Schedule Extended API (FSL.ScheduleService.scheduleExtended) to schedule a Service Appointment (SA) whose Arrival Window is set beyond the org's configured scheduling horizon (for example, 31 days), the action returns "No candidates found" — if that SA has a 
same-day dependency (such as "Start After Finish And Same Day") on another SA that is still flexible.

The flexible SA's search window is capped at its Earliest Start Permitted + the scheduling horizon, so it can never reach the fixed, out-of-horizon date required for the same-day match — resulting in zero valid candidates, even though Get Appointment Booking Slots may still return a slot.

This is expected product behavior.

Note: This article applies to scheduling scenarios where the SA's Arrival Window was set before initiating the booking flow. If the Arrival Window was changed after slot retrieval, a separate known issue may apply — contact Salesforce Support for that scenario.

Resolution

Use the following workarounds to ensure all Service Appointments in the dependency chain fall within the org's configured scheduling horizon. Options are listed in order of preference.

1. Align dates across the dependency chain: set the predecessor SA's Earliest Start Permitted and/or Arrival Window to the same timeframe as the fixed-arrival SA, so its search window covers that date too.
   - Note: aligning dates may allow Get Candidates to return results, but Book Appointment may still fail if the Arrival Window still exceeds the horizon on the SA being booked.

2. Temporarily adjust the Earliest Start Permitted on the other SA in the chain so the horizon window does not need to be exceeded (that is, keep both SAs within the configured horizon limit, such as 31 days) — this is required if Book Appointment specifically must succeed.

3. Where possible, schedule within the configured horizon (for example, within 31 days) rather than far outside it (for example, at ~62 days).

Knowledge Article Number

005459963

 