Maintenance Plan Work Orders Not Generated Ahead of Due Date – Winter ’27

Publiseringsdato: Oct 21, 2026
Beskrivelse
After upgrading to Winter ’27, auto-generate Maintenance Plans with a Generation Horizon (GH) set to blank or 0 may stop creating Work Orders ahead of schedule.

What Changed
• Before Winter ’27: The background job picked up all Maintenance Plans on every run (runs every 8 hours), regardless of when the Maintenance Work Rule (MWR) Next Suggested Maintenance Date (NSMD) was due. Work Orders were created for the full Generation Timeframe window.
• After Winter ’27: The job first checks if the MWR’s NSMD falls within the Generation Horizon before selecting a plan:
NSMD <= Today + GH
When GH is blank or 0, the plan is not selected until the NSMD date is reached, even if the Generation Timeframe is configured to create Work Orders further in advance.
Work Order Generation Conditions For Work Orders to generate, both conditions must be met:
  1. NSMD <= Today + Generation Horizon
  2. NSMD >= Today - Generation Timeframe
Result: Work Orders are created for dates from Today up to, but not including: Today + GH + Generation Timeframe
This change prevents the job from processing Maintenance Plans that are not yet due for Work Order generation.

Who is Affected
• Maintenance Plans with Maintenance Work Rules (plan-level or asset-level)
• Auto-generate is enabled on the plan
• Generation Horizon is smaller than the previous lead time (includes blank or 0 horizon)
• Work Orders were previously expected ahead of the MWR due date
Løsning
Option 1 — Update the Generation Horizon (Recommended)
Best for permanently configuring the desired lead time.
  1. Navigate to the Maintenance Plan record and click Edit.
  2. In Generation Horizon, enter the number of lead-time days needed (e.g., enter 6 if Work Orders previously generated 6 days early).
  3. Click Save.
Note: The plan is selected on the next run when NSMD <= Today + GH. A larger GH may create more occurrences in one batch if paired with a long Generation Timeframe.

Option 2 — Manually Adjust Next Suggested Maintenance Date (One-Time Fix)
Best for immediate processing of specific plans without changing GH.
  1. Open the Maintenance Work Rule linked to the Maintenance Plan and click Edit.
  2. Set Next Suggested Maintenance Date to Today, or to a date no earlier than Today - Generation Timeframe.
  3. Click Save.
Note: This addresses individual cases only and shifts the schedule’s starting point (the WO is created for the new date rather than the original due date). Use Option 1 for a permanent fix.