Managing Enablement Measures for Outcomes and Milestones
Outside of Enablement programs, you create Enablement measures and specify the objects, fields, and field values you want to track. In programs, you specify the criteria for completing an outcome or milestone that references measures. For example, specify the target values to achieve or the number of records to evaluate. You can reuse measures across multiple programs or multiple milestones in the same program.
Required Editions
| Available in: Lightning Experience |
| Enablement is available in Developer Edition with a limited number of add-ons. It is also available with Sales, Service, or the Salesforce Platform in: Enterprise, Performance, Unlimited, and Einstein 1 Sales Edition Editions for an additional cost |
| Enablement Lite is available with Sales in: Enterprise, Performance, and Unlimited Editions |
| Partner Enablement is available in Developer Edition with a limited number of add-ons. It is also available with Sales, Service, or the Salesforce Platform in: Enterprise, Performance, and Unlimited Editions for an additional cost. A supported PRM add-on license is required. |
Measures for Outcomes and Milestones
For the outcome and each incremental milestone in your Enablement program, select the appropriate measures.
For the Target field, specify the number of times that a user must fulfill the measure’s criteria to complete the outcome or milestone. For example, if you set an outcome for users to win 3 deals by the completion of the program, set the Target to 3. Users see the target when taking the program. For example, for a target of 10, users see 0/10 until they progress toward the goal.
For outcomes and milestones that use average-based measures, also specify a value for Minimum Sample Size. The minimum sample size represents the number of records that you want to evaluate for calculating the average value that satisfies the outcome or milestone. For example, if you want users to achieve an average deal size of $50,000 after closing 4 deals, set these values.
- For Minimum Sample Size, enter 4.
- For Measure Target, enter 50,000.
For outcomes and milestones that use Einstein Conversation Insights (ECI) measures, specify a Day value that’s less than 180. You can track ECI measures only up to 180 days in the past.
For composite outcomes and milestones, select multiple measures and specify a calculation logic to aggregate the measures’ results. The aggregated measure result is compared against the target for the composite outcome or milestone to track a user’s progress. See Managing Composite Outcomes and Milestones.
Multiple Milestones That Reference the Same Measure
You can insert multiple milestones that reference the same measure. When a user taking the program progresses toward one of these milestones, their progress counts toward all milestones that reference that measure. A user’s progress is measured cumulatively.
For example, let’s say that your program requires a user to win an increasing number of opportunities as the program progresses.
| Milestone | Day of Program |
|---|---|
| Win 1 opportunity | 10 |
| Win 3 opportunities | 20 |
| Win 10 opportunities | 30 |
In this example, each milestone references the same measure that tracks opportunities won. When a user wins their first opportunity, the program shows that the first milestone is complete. The program also shows that one opportunity has been won for both the second and third milestones. For the user, it can look as if they’re getting a head start on upcoming milestones. For the Enablement admin, the same result appears in their analytics.
To make sure that your users are achieving the appropriate milestones, adjust the Target for each subsequent milestone. In this example, you want to make sure that a user wins 1 opportunity first, then 3 more opportunities, and finally 10 more opportunities. To account for that incremental achievement, adjust the Target values in each milestone.
| Milestone | Day of Program | Measure Target |
|---|---|---|
| Win 1 opportunity | 10 | 1 |
| Win 3 opportunities | 20 | 4 |
| Win 10 opportunities | 30 | 14 |